new pavement on newton street

September 1 to September 7, 2019

The Weston Department of Public Works continued to fulfill its mission to construct and maintain the physical infrastructure that provides for the public's health and safety, to protect the environment, and to enhance the quality of life and ensure that Weston continues to be a desirable place in which to live and conduct business. The following is the weekly report, by division:

 
dpw seal

2019 Roadway Reconstruction Program

  • Wellesley Street at School Street Intersection - ADA ramps outstanding. Hydroseeding  and pavement marking work scheduled for September 16;
  • Newton Street (from Wellesley Street to approximately #150 Newton) - Hydroseeding  and pavement marking work scheduled for September 16;
  • Bogle Street - National Grid work completed. NGrid will permanent trench pave trenches before November 26.  Anticipate any other pavement deficiencies will be address next spring before the Rubber Chip Seal Treatment is installed;
  • Pigeon Hill RoadAnticipate mobilizing Paving Contractor to this area the week of September 30;
  • Hilltop Road – See Pigeon Hill Road timeline;
  • Old Road – See Pigeon Hill Road timelines;
  • Gail Road – Roadway reconstruction work schedule has not yet been set;
  • Pembroke Road - National Grid replacing the gas main and services prior to roadway work.  Anticipate their work being completed the week of September 16.  See Pigeon Hill Road timelines;
  • Merriam Street (Sunset Road to Silver Hill Road) – There are a lot of moving parts that need to be completed prior to the roadway reconstruction taking place, including:
    • complete roadway drainage work between Westland Road and house no. 189 +/-, Westland Road and house no. 217, and house no. 245 +/- to Hallet Hill Road;
    • Merriam Street Culvert Replacement over Cherry Brook;
    • Water gate replacements on Merriam Street at Cherry Brook Road (holding utility pole is required);
    • sidewalk (southerly section between Westland Road and Sunset Road which require easements) 

Completed Roadways

  • Cherry Brook Road;
  • Pollywog Lane;
  • Sylvan Road (entire length);
  • Glen Road (Wellesley Street to Shady Hill Road)
  • Cliff Road and Brown Street - Rubber chip seal; 


Town Center Improvement Project

  • Find construction updates - sign up for "Town Center Construction Project" email/text notifications Weston.org/StayInformed or visit project web page at Weston.org/TownCenter for three-week look ahead
    • Verizon manhole/vault installation continues between Church St and Town House Rd;
    • Conduit installation continues just west of School Street;
    • Traffic Management Plans - modified daily to maximize available parking for the businesses

Additional Road Work Not Affiliated with the Town's Roadway Program

  • See updates in "State/Utility Project Work" for projects impacting roadways:
    • Conant Road (rail trail) 
    • Concord Road/ Church Street parking at spurs (rail trail access)
    • National Grid gas main work
  • See updates in "Ongoing DPW Projects" for water/drainage, etc. work at:
    • Newton Street
    • Legacy Trail
    • Water main/drainage projects
  • See updates in "Consultant Work" for larger projects at:
    • Rt. 20 and Rt. 30 TIP projects
    • Ash Street sidewalk
1
MCRT trail sign

State/Utility Project Work

  • Continuing to coordinate with Eversource on a number of outstanding issues in Town including double poles, poles guyed into trees, leaning poles and pole guyed with rope (Merriam Street), Hazard trees at/near power lines, etc.;
  • Rail Trail Projects:  
    • Eversource and DCR Rail Trail Project – substantially complete;
    • Conant Road Underpass Project (DCR) – There is still work to complete below the roadway including treatment work to the interior culvert, shoulder work, etc.  The punchlist of work needing completion is ongoing;
    • Concord Road Spurs and Church Street Spurs Parking Areas (Town) –  Working on punchlist work as well as benches and bike racks, etc;
    • DPW / DCR coordinated with MassDOT to address concrete spall and graffiti issues for Concord Road and Church Street bridges over the Rail Trail
  • National Grid gas relay projects proposed for construction during the 2019 Construction Season:
    • Church Street (at/about Pigeon Hill Road) - work ongoing; 
    • Newton Street - work is ongoing
    • Pembroke Road - work is ongoing
    • Bogle/Winter - work completed
    • Sherburn Circle, Wellesley Street (669-654) - work tentatively scheduled to be begin the week of September 23;
    • Concord Road (1-81) - schedule is unknown 
  • National Grid has submitted several permits for repairing long-standing gas leak locations.
 
DPW employees installing a drainage pipe

Ongoing DPW Projects

  • Wireless Meter Reading - All contracts are in place (3) and the permits for collector are in progress. Coordination with town accounting hardware is also ongoing (MUNIS). Notices for meter work and scheduling will be going out soon. Then the installation of collector sites, meters and radios will occur over the next several months, and then activation of the system. See Weston.org/WaterMeters for more information; 
  • Overseeing consultants’ work on the Southside Drainage Project - Anticipate work continuing on the pipe work just north of Ledgewood.  Town Engineer has coordinated with impacted residents.  Next phase of this project will be the inlet structure at/about 19 Pond Brook Circle;
  • Cemetery Restoration Phase II - headstone rehabilitation contract ongoing;
  • Newton Street Drainage - Town Engineer is working with several properties owners and others to secure easement rights for Phase II and Phase III drainage work; 
  • Merriam Street Drainage work (between Westland Road and Cherry Brook Road) – Drainage work still needed on the Hallet Hill Road portion of Merriam Street.  Town Engineering working with Town Counsel;
  • Legacy Trail Project -  construction to begin soon;
  • Water: Lead Link Removals (over 60 locations) – Initial work completed.  Cleanup and final trench paving work outstanding.  It is anticipated that this work will be substantially completed by beginning of September with permanent trenching paving work still to be completed;
  • Water: Lantern Lane and Old Coach Road – Anticipate starting this work September 16

Completed Projects

  • Black Oak Pump Station
  • Paines Hill Water Tank Improvement Project
  • Loring Road Drainage work (by #83)
 
a birds-eye view of the town center plan

Consultant Work Managed by DPW

  • Overseeing consultant work on Proposed Route 30 Roadway Reconstruction TIP Project - roadway, sidewalk, drainage improvements, intersection improvements, etc. A brief summary of the progress to date was provided to the Board of Selectmen on July 30.  Anticipate being before the Board at the first October meeting to solicit comments prior to the formal 25% Submission to MassDOT in the Winter of 2019. Project info at weston.org;
  • Overseeing consultant work on Proposed Route 20 Intersection Improvement TIP Project - (signal at Boston Post Road/Wellesley Street/Boston Post Road By-Pass) - A brief summary of the progress to date was provided to the Board of Selectmen on July 30.  Anticipate being before the Board at the September 10 meeting to solicit comments prior to the formal 25% Submission to MassDOT in the Winter of 2019. Project info at weston.org;
  • Overseeing several sidewalk design projects -  (Merriam Street and Warren Avenue) – Funding secured for the work; culvert replacement and drainage work on Merriam needs to take place; sidewalk project needs to be coordinated with roadway work. Warren Ave on hold;  
  • Overseeing consultant design and permitting for Concord Road Culvert replacement which has impacts on the Warren Avenue and Merriam Street culverts - decision matrix tabling being evaluated.  Engineering presented findings to Board of Selectmen and the Conservation Commission;
  • Overseeing consultant design and permitting for Ash Street Sidewalk Project - Design ongoing.  Consultant to presented progress prints to Traffic and Sidewalk Committee, but drainage, length of crosswalk and curbing issues/comments from DPW Director need to be resolved.  Town Engineer has outreached to MWRA about secure rights / easements to address previously mentioned concerns;
  • Overseeing consultant design and permitting for Water Distribution Master Plan.  Presented at the Board of Selectmen on July 30 to discuss recommendations of the report.  Action item is to prepare Article for December 2019 Special Town Meeting;
  • Overseeing consultant design and preparation of specification for Cemetery Tomb Restoration.  Draft plans provided and comments provided back to consultant
 
engineering drawings for stormwater drainage

Engineering

  • Currently reviewing 8 Stormwater Permits;
  • Currently issued 59 Stormwater permits which also requires construction inspection; 
  • Set up a temporary special speed zone on School Street between Brook School Apartments and Wellesley Street to 30 mph and perform speed study
  • Traffic Engineering Consultant Services - two assignments issued; 
  • Working with the Town’s Traffic and Sidewalk Committee on several items:  Love Lane, Chestnut Street, Sunset Road, Wellesley Street at Route 30 signal, mirrors, stop sign requests, sidewalk requests, crosswalk requests, etc.;
  • Ongoing Engineering Drainage Designs:
    • Hallet Hill at Merriam Street – created hydrologic model and investigated existing drainage system;
    • Pinecroft at Conant Road – worked on hydrologic model and laid out proposed drainage system;
    • Merriam Street - southerly end drainage (just north of Fox Chase Road) – surveyed some existing grades for contractor
1
dig safe flags

Water Division

  • Completed approximately 22 DigSafes
  • Performed weekly samples (3), monthly water samples at tanks, and station/tank inspections;
  • Conducted 1 final read;
  • Inspected 1 new water service and installed meter and valves;
  • Continue to work on water billing;
  • Shut down water main in Town Center so contractor could make repairs to main that was hit;
  • Conducted Annual Lead and Copper Sampling testing cycle;
  • Installed 1 new valve before meter for resident 
 
lawn mower cutting grass

Park and Cemetery Division

  • Cut and trimmed grass at Linwood Cemetery and other park and cemetery locations;
  • Cleaned and serviced equipment;
  • Continued updating the cemetery spreadsheets for interments and lot owners
 
recycle more banner

Solid Waste and Recycling Division

  • Processed 1, 100-yard solid waste dumpster totaling 23.5 tons;
  • Picked up municipal office recycling – 1,140 lbs;
  • Picked up Town office and select Town park solid waste – 1,000 lbs.;
  • Processed 1 cardboard container – 5.55 tons;
  • Processed 1 glass container – 4.19 tons;
  • Ran 1 shuttle for grass/leaves – 13.20 tons;
  • Ran 1 shuttle for brush /logs – 3.73 tons;
  • Processed 1 metal container – 6.17 tons;
  • Assisted with the pickup of various donations including clothing, electronics, books and bikes – 920 lbs;
  • Assisted with pickup of Weston textiles – 1,460 lbs;
  • Electronics and appliances w/Freon – 1.49 tons;
  • Processed the pickup of CRT electronics – 2.30 tons;
  • Processed pickup of light bulbs – 1,120 lbs;
  • Organized and maintained order in swap shed;
  • Cleaned the trailer pit as needed;
  • Pick up litter and cleaned up around the site as needed;
  • Cut and trimmed the grass around the property
2
rubber chip seal

Highway/Stormwater Divisions

  • Hot patching potholes:  South Avenue and Newton Street;
  • Respond to Misc. calls for service: 12;
  • Fallen tree / branch removal from roadway and/or culverts: North Avenue, Merriam Street by Brush Dump, Church Street, Newton Street at Young Road;
  • Traffic signage and maintenance repairs:  Winter Street, Radcliff, Clearing in Middle sections;
  • Set up Detour for: Cases Corner, School Street, Newton, Wellesley Street;
  • Inspect miscellaneous tree locations for possible action: Church Street;
  • Respond to Flooding calls:  Summer Street by Loring Road;
  • Mowing and trimming including flail mowing:  Middle and North sections & Highland Street, Brown Street, and Winter Street;
  • Cooks Pond Pump Station:  1 restart and remove clogging;
  • Assist Paving Contractor:  Sidewalks - Wellesley and School Street and Newton Street;
  • Assist Structure Contractor:  Cleanup and Transport to waste, used castings;
  • Assist Bee Removal Contractor – Town House Road;
  • Apply Temp. Pavement Markings:  Cases Corner, Wellesley, Newton Street, and Ash Street;
  • Assist Engineering:  Drain Valve on Pond Brook Circle
 
maintenance of a DPW truck

Vehicle Maintenance Division

  • Performed routine maintenance (fluid services, tires and brakes, exhaust, steering and suspension, exterior trim work and electrical repairs on 3 school buses, 2 police vehicles, and 6 DPW trucks and other equipment, noting that the DPW Vehicle Maintenance Division is responsible for over 122 pieces of rolling stock for the Town;
  • Performed 2 major repairs on vehicles with Major/Significant maintenance activity:  Shop Facility grease lines, HH-15 exhaust manifold
 

Want more?

Don't miss another weekly update.
Easily subscribe today at www.weston.org/list.aspx

Comments/Suggestions: contact webmaster@westonmass.org

 
Powered by
CivicSend - A product of CivicPlus