DPW building

April 21 - April 27, 2019

The Weston Department of Public Works continued to fulfill its mission to construct and maintain the physical infrastructure that provides for the public's health and safety, to protect the environment, and to enhance the quality of life and ensure that Weston continues to be a desirable place in which to live and conduct business. The following is the weekly report, by division:

 
dpw seal

2019 Roadway Reconstruction Program (Round 1)

  • Cherry Brook Road, Pollywog Lane, Glen Road (Wellesley Street to Shady Hill Road) – anticipate completing drainage work (sub-drain installation) over the next couple of weeks;
  • Gail Road -  National Grid needs to complete tie-in from old gas main to new gas main installed last June; 
  • Pembroke Road - National Grid needs to replace existing gas main prior to roadway work;  
  • Water gates at Merriam Street and Cherry Brook Road delayed due to need to hold water utility pole adjacent to water gates;  
  • Preparation work (repair of deteriorated pavement) on Brown Street and Cliff Road is anticipated to occur the week of April 15th;
  • The Town’s Chip Seal contractor anticipated being mobilized in July
  • National Grid is anticipated to be replacing the leaking gas main at Bogle Street (from Winter Street to just south of the culvert) in advance of the Chip Sealing Program 
1
detour sign

State/Utility Project Work

  • Continuing to coordinate with Eversource on a number of outstanding issues in Town including double poles, poles guyed into trees, leaning poles and pole guyed with rope (Merriam Street), Hazard trees at/near power lines, etc.;
  • Continuing to coordinate with Eversource and MassDCR on the Rail Trail Project:  
    • punchlist items are anticipated to be finished in the spring when the next phase of construction picks up. 
    • DCR is responsible for the Rail Trail / Conant Road Underpass Construction. DCR and its consultant held a pre-construction meeting on April 11;
    • It is anticipated that work will be started April 2019 and be completed by July 2019. Conant Road will be closed for a period of time during construction and detours will be in place; 
    • Several contracts/contractors will be working on the rail trail – Eversource’s contractor, DCR’s contractor for the trail, DCR’s contractor for the Conant Road Underpass, and the Town’s contractor for the Concord Road and Church Street spur parking areas
    • DPW is attempting to coordinate with MassDOT to address concrete spall and graffiti issues for Concord Road and Church Street bridges over the rail trail 
  • DPW met with National Grid Representatives the week of January 21 to review 2019 construction season. NGrid to supply DPW with updated work schedule. NGrid’s gas relay projects proposed for construction during the 2019 Construction Season:
    • Newton Street - work is ongoing
    • Gail Road - work anticipated to be completed in April/May
    • Pembroke Road - work will start after Gail Road completed 
    • Sherburn Circle, Wellesley Street (669-654), and Concord Road (1-81) - schedule is unknown 
  • National Grid has submitted several permits for repairing long-standing gas leak locations. These are currently under review and are anticipated to begin work in April
 
DPW employees installing a drainage pipe

Ongoing DPW Projects

  • Black Oak Pump Station – work continues with electrical and gas; 
  • Overseeing consultants’ work on the Southside Drainage Project - Anticipate receiving consultant design package Phase II by week of April 22nd and advertise project shortly thereafter;
  • Paines Hill Water Tank Improvement Project - Punchlist work remaining – electrical and plumbing. Electrical work anticipated to start and be completed over the next several weeks;
  • Cemetery Restoration Phase II - headstone rehabilitation contract ongoing;
  • Newton Street Drainage - First piece of drainage work by Land Sake is under construction – Trench paving work outstanding for Phase I.  Town Engineer is working with several properties owners and others to secure easement rights for Phase II and Phase III drainage work; 
  • Loring Road Drainage work (by #83) - No work completed this period;
  • Merriam Street Drainage work (at/about Westland Road) – Pre-construction meeting with contractor on April 26th.  Set up message boards week of 4/29
 
a birds-eye view of the town center plan

Consultant Work Managed by DPW

  • Overseeing consultant work on Proposed Route 30 Roadway Reconstruction TIP Project - roadway, sidewalk, drainage improvements, intersection improvements, etc.  Work has begun on the Functional Design Report (a MassDOT required submission). Consultant met with Traffic and Sidewalk Committee during the February meeting to discuss direction. Planning on meeting with MassDOT D-6 Office on April 12th to discuss progress. Project info at weston.org;
  • Overseeing consultant work on Proposed Route 20 Intersection Improvement TIP Project - (signal at Boston Post Road/Wellesley Street/Boston Post Road By-Pass) - intersection improvements, etc. Work has begun on the Function Design Report (a MassDOT required submission).Consultant/Town Engineer met with Traffic and Sidewalk Committee during April meeting to discuss direction of design and then setup a MassDOT D-6 meetingProject info at weston.org;
  • Overseeing consultant design and preparation of specifications for Proposed Concord Road Spurs and Church Street Spur Rail Trail Parking Areas - Contract awarding process and signature in progress. Anticipate holding a pre-construction meeting the beginning of May; 
  • Overseeing several sidewalk design projects -  (Merriam Street and Warren Avenue) – Funding secured for the work; culvert replacement and drainage work needs to take place; sidewalk project needs to be coordinated with roadway work. Meeting to discuss Warren Avenue proposed sidewalk and various constraints to be discussed at next Traffic and Sidewalk Committee meeting;
  • Overseeing consultant design work for drainage work for construction season 2016 (Newton Street and Merriam Street) - Continue to attempt to secure required easements on Newton Street.  First piece of drainage work by Land Sake is nearing completion – see above for Phase I update.  Work on Glen Road (Wellesley Street to Shady Hill Road) is nearing completion;
  • Overseeing consultant concept/design work for the Town Center Improvement Project -  March Special Town Meeting approved construction funds. Awaiting to award contract. Project info and plans can be found at   weston.org/TownCenter;
  • Overseeing consultant work on setting up RFPs for Wireless Meter Reading - meter replacements and meter installation (approximately 1700). AMI and meter purchase contracts secured.  AMI installation bids opened;  Installation of Collector Sites (tank locations and Wellesley Street), installation of meters and radios over the next several months, and then activation of the system; 
  • Overseeing consultant design and permitting for Concord Road Culvert replacement which has impacts on the Warren Avenue and Merriam Street culverts - decision matrix tabling being evaluated.  Engineering presented findings to Board of Selectmen and the Conservation Commission. Funding pending Annual Town Meeting vote;
  • Overseeing consultant design and permitting for Ash Street Sidewalk Project - Design ongoing.  Consultant to presented progress prints to Traffic and Sidewalk Committee, but drainage, length of crosswalk and curbing issues/comments from DPW Director need to be resolved.  Town Engineer has outreached to MWRA about secure rights / easements to address previously mentioned concerns;
  • Overseeing consultant design and permitting for Water Distribution Master Plan.  Received draft report and is currently under review;
  • Overseeing consultant design and preparation of specification for Cemetery Tomb Restoration.  Draft plans provided and comments provided back to consultant
 
engineering drawings for stormwater drainage


Engineering

  • Currently reviewing 8 Stormwater Permits;
  • Currently issued 59 Stormwater permits which also requires construction inspection; 
  • Attempting to convince MassDOT to reconsider its decision to not lower the special speed zone on School Street between Brook School Apartments and Wellesley Street which a temporary regulation would need to be setup.  Board of Selectmen approved temporary regulation at October 23rd meeting.  Next action item is to get approval from MassDOT; 
  • Traffic Engineering Consultant Services contract signed by Town; 
  • Working with the Town’s Traffic and Sidewalk Committee on several items:  Love Lane, Chestnut Street, Sunset Road, Wellesley Street at Route 30 signal, mirrors, stop sign requests, sidewalk requests, crosswalk requests, etc.;
1
dig safe

Water Division

  • Completed approximately 50 DigSafes;
  • Performed weekly samples (3), monthly water samples at tanks, and station/tank inspections;
  • Conducted 4 final reads;
  • Installed 3 summer service meters and turned water on;
  • Witnessed 2 water samples taken from a new water service line including 1 pressure test;
  • Continue to read meters;
  • Continue to hydrant flush
 
calla lily

Park and Cemetery Division

  • 5 graves dug with casket interments;
  • Continued with spring cleanup in Linwood Cemetery and other Parks and Cemetery locations;
  • Assisted Solid Waste and Recycling Division with picking up solid waste at Town Buildings and the push down of containers;
  • Loam and seeded winter graves;
  • Continued updating the cemetery spreadsheets for interments and lot owners
 
recycle more banner

Solid Waste and Recycling Division

  • Processed 1, 100-yard solid waste dumpster totaling 23.20 tons;
  • Picked up municipal office recycling – 1,740 lbs;
  • Picked up Town office and select town park solid waste – 1,680 lbs. (140 lbs for Town-wide Cleanup);
  • Processed 1 newspaper container – 10.73 tons;
  • Ran 1 shuttle for grass/leaves – 11.62 tons;
  • Processed 1 metal container – 5.04 tons;
  • Assisted with the pickup of various donations including clothing, electronics, books and bikes – 240 lbs;
  • Assisted with pickup of Weston textiles – 2,460 lbs;
  • Organized and maintained order in swap shed;
  • Cleaned the trailer pit as needed;
  • Pick up litter and cleaned up around the site as needed;
  • Started the Spring Cleanup around the building and property;
  • Brush Dump opened on 4/27/19 with 24 vehicles
2
diagram showing how to repair a sinkhole

Highway/Stormwater Divisions

  • Hot patching potholes: Aberdeen and Concord Road;
  • Skin Overlay degraded roadway surfaces:  37 Bakers Hill, West Cliff @ Cliff, Willard Road, Colchester, October;
  • Respond to Misc. calls for service: 
  • Fallen tree / branch removal from roadway and/or culverts:  Gail Road and Concord Road;
  • Traffic signage and maintenance repairs:  Rail Road Crossings at Conant Road and Viles Street;
  • Set up Detour for:  Plymouth Road;
  • Inspect miscellaneous tree locations for possible action: Concord Road, Chiltern Road, Shady Hill Road, Wellesley Street, Forest Ridge;
  • Street Sweeping:  Week 4 Sweeping Schedule;
  • Repair/Clean/Inspect drain manhole / catch basin: Plymouth Road;
  • Respond to Flooding calls:  Chiltern Road, Summer Street, Ridgeway Road;
  • Stormwater Conditions –  Falmouth Road (silt sacks and cleanup),  Sherburn (silt sack and wattle);
  • Pave Basins:  Plymouth Road;
  • Oversee Drain Cleaning and Video:  Chiltern Road, Sears Road, Conant Road;
  • Check and Clear waterways:  All sections 1 time;
  • 45 Public Road Islands – Cleanup and Ready for new growing season- completed over 3 week period);
  • Clean and service equipment:  2 times;
  • DIGSafe Markouts:  Plymouth Road;
  • Cut Driveway Aprons and Intersections:  Cherry Brook and Pollywog;
  • Assist structure contractor:  Cherry Brook and Pollywog;
  • Deliver Construction Notices:  Cherry Brook, Pollywog, Aspen and Juniper;
  • Assist Park/Cemetery – with burial;
  • Relieve Drain Blockage:  Lexington Street
 
maintenance of a DPW truck

Vehicle Maintenance Division

  • Performed routine maintenance (fluid services, tires and brakes, exhaust, steering and suspension, exterior trim work and electrical repairs) on 9 school buses, 1 police vehicles, and 13 DPW trucks and other equipment, noting that the DPW Vehicle Maintenance Division is responsible for over 122 pieces of rolling stock for the Town;
  • Performed 1 major repair on vehicles with Major/Significant maintenance activity: H-23 replace injector and hose;
  • Performed 1 repair on sanders/plows: H-14removed and sealed up sander for the summer
 

Want more?

Don't miss another weekly update.
Easily subscribe today at www.weston.org/list.aspx

Comments/Suggestions: contact webmaster@westonmass.org

 
Powered by CivicSend - A product of CivicPlus