DPW building

December 31, 2019 - January 5, 2019

The Weston Department of Public Works continued to fulfill its mission to construct and maintain the physical infrastructure that provides for the public's health and safety, to protect the environment, and to enhance the quality of life and ensure that Weston continues to be a desirable place in which to live and conduct business. The following is the weekly report, by division:

 
detour sign

State/Utility Project Work

  • Continuing to coordinate with Eversource on a number of outstanding issues in Town including double poles, poles guyed into trees, leaning poles and pole guyed with rope (Merriam Street), Hazard trees at/near power lines, etc.;
  • Continuing to coordinate with Eversource and MassDCR on the Rail Trail Project:  
    • all that remains are punchlist items, which are anticipated to be finished in the spring when the next phase of construction picks up with the opening of the Conant Road underpass and the two parking areas. Work is anticipated to start March/April and take about 4-6 weeks. Conant Road will be closed for a period of time during construction and detours will be in place;
    • DPW Director is hopeful that, through much work of the Rail Trail Advisory Committee, the final plans for the parking areas will be ready for advertising soon and have an anticipated bid opening by the end of February
  • National Grid’s gas relay projects proposed for construction during the 2019 Construction Season, all which remain subject to ongoing labor dispute: Newton Street, Gail Road, Pembroke Road, Sherburn Circle, Wellesley Street (669-654), and Concord Road (1-81)
 
DPW employees installing a drainage pipe

Ongoing DPW Projects

  • Black Oak Pump Station – Shop drawing submittals and review of construction sequence continues. National Grid has indicated a delay in extending gas service which is being appealed to the state Dept. of Public Utilities by the Town and its Representative. The Town is waiting for a response; 
  • Overseeing consultants’ work on the Southside Drainage Project - The necessary easements for Phase II of the project have been secured.  The permitting will be conducted with construction anticipated for January 2019. It is anticipated that the project will be before the Conservation Commission on a meeting in January for Phase II work;
  • Paines Hill Water Tank Improvement Project - Punchlist work remaining – electrical and plumbing.  Bids for electrical work received Oct. 19th and Town is proceeding with award with work anticipated to started and completed over the next several weeks;
  • Cemetery Restoration Phase IIHeadstone rehabilitation contract ongoing with work anticipated to begin next spring;
  • Newton Street Drainage - First piece of drainage work by Land Sake is under construction – Trench paving work outstanding for Phase I.  Town Engineer is working with several properties owners and others to secure easement rights for Phase II and Phase III drainage work; 
  • Loring Road Drainage work (by #83) - Work in Loring Rd. was scheduled to begin the week of Dec. 31st;
  • Glen Road Drainage work (Shady Hill Road to Wellesley Street) – Totals:  5 drain manholes, 4 catch basins, and an additional 110-feet of drainage piping installed.  Crews encountered ledge in 60-70% of excavation, which is slowing down progress
 
a birds-eye view of the town center plan

Consultant Work Managed by DPW

  • Overseeing consultant work on Proposed Route 30 Roadway Reconstruction TIP Project - roadway, sidewalk, drainage improvements, intersection improvements, etc.  Work has begun on the Functional Design Report (a MassDOT required submission). Scheduled meeting on January 17th to discuss progress. Project info at weston.org;
  • Overseeing consultant work on Proposed Route 20 Intersection Improvement TIP Project - (signal at Boston Post Road/Wellesley Street/Boston Post Road By-Pass) - intersection improvements, etc.  Survey  work has continued and needs to confirm drainage inverts.  Work has begun on the Function Design Report (a MassDOT required submission). Project info at weston.org;
  • Overseeing consultant design and permitting on Proposed Concord Road Spurs and Church Street Spur Rail Trail Parking Areas - Overseeing consultants’ work on proposed parking areas for the rail trail.  Preliminary plans developed, modified and were presented to Rail Trail Advisory Committee.  Chair will provide comments to consultant to incorporate into revised plan set.  Desire is to have a permitted set of plans for a bid opening the end of February 2019. Conservation Commission discussions are ongoing with agent; 
  • Overseeing several sidewalk design projects -  (Merriam Street and Warren Avenue) – Funding secured for the work; culvert replacement and drainage work needs to take place; sidewalk project needs to be coordinated with roadway work. Meeting to discuss the Warren Ave. proposed sidewalk and various constraints will be discussed at the next Traffic and Sidewalk Committee meeting;
  • Overseeing consultant design work for drainage work for construction season 2016 (Newton Street and Merriam Street) - Continue to attempt to secure required easements on Newton Street.  First piece of drainage work by Land Sake is nearing completion – see above for Phase I update.  Work on Glen Road (Wellesley Street to Shady Hill Road) started and underway;
  • Overseeing consultant concept/design work for the Town Center Improvement Project -  Moving forward on rebidding the project with an anticipated bid opening on February 28th. A Special Town Meeting to approve construction funds is anticipated for March 18th. Project info and plans can be found at   weston.org/towncenter;
  • Overseeing consultant work on setting up RFPs for Wireless Meter Reading - meter replacements and meter installation (approximately 1700).  Consultant preparing an RFP for Installation of AMI and meters. Working on outreach to those abutters impacted by the pole and collector locations (i.e. at the existing tanks or former tank locations); 
  • Overseeing consultant design and permitting for Concord Road Culvert replacement which has impacts on the Warren Avenue and Merriam Street culverts - decision matrix tabling being evaluated.  Engineering presented findings to Board of Selectmen and the Conservation Commission;
  • Overseeing consultant design and permitting for Ash Street Sidewalk Project - Design ongoing.  Consultant to presented progress prints to Traffic and Sidewalk Committee;
  • Overseeing consultant design and permitting for Water Distribution Master Plan.  Consultant gathering data and setting up the calibration of the water system hydraulic model including. The vision for this plan is to lay out short term and long term capital plans relating to the water distribution system including water mains, gates, meters, water tanks, etc.  Anticipated final report has been pushed one month by consultant due to hydraulic modeling concerns;
  • Overseeing consultant design and preparation of specification for Cemetery Tomb Restoration.  Draft plans provided and comments provided back to consultant
 
engineering drawings for stormwater drainage


Engineering

  • Currently reviewing 12 Stormwater Permits;
  • Currently issued 59 Stormwater permits which also requires construction inspection; 
  • Attempting to convince MassDOT to reconsider its decision to not lower the special speed zone on School Street between Brook School Apartments and Wellesley Street which a temporary regulation would need to be setup.  Board of Selectmen approved temporary regulation at October 23rd meeting.  Next action item is to get approval from MassDOT; 
  • Working with the Town’s Procurement Officer, prepare an RFP for Traffic Engineering Consultant Services
  • Regarding ADA parking stall at Kendal Green Parking Lot due to non-use - state denied request for a waiver, therefore, handicap stalls will remain; 
  • Working with the Town’s Traffic and Sidewalk Committee on several items:  Love Lane, Chestnut Street, Sunset Road, Wellesley Street at Route 30 signal, mirrors, stop sign requests, sidewalk requests, crosswalk requests, etc.;
1
an example of a residential water meter

Water Division

  • Completed approximately 15 DigSafes;
  • Performed weekly samples (3), monthly water samples at tanks, and station/tank inspections;
  • Conducted 3 final reads;
  • Continued reading water meters;
  • Cleaned out water gates and replaced broken covers;
  • Responded to 2 water service leaks;
  • Responded to a broken meter leaking call;
  • Replaced a large meter register
 
three purple calla lilies

Park and Cemetery Division

  • 1 grave dug with casket interment;
  • Cleaned and serviced equipment;
  • Continued cleaning up in Linwood Cemetery and other parks and cemetery locations;
  • Continued updating the cemetery spreadsheets for interments and lot owners
 
recycle more banner

Solid Waste and Recycling Division

  • Processed 2, 100-yard solid waste dumpsters totaling 40.67 tons;
  • Picked up municipal office recycling – 1,680 lbs;
  • Picked up Town office and select Town park solid waste –2,140 lbs.;
  • Processed 1 cardboard container – 4.90 tons;
  • Processed 1 glass container – 5.01 tons;
  • Processed 1 bulky plastic container – 4.08 tons;
  • Ran 1 shuttle for brush /logs – 7.66 tons;
  • Processed 1 metal container – 4.41 tons;
  • Process 1 container of scrap wood – 5.00 tons;
  • Assisted with the pickup of various donations including clothing, electronics, books and bikes – 2,550 lbs;
  • Assisted with pickup of Weston textiles – 1,020 lbs;
  • Organized and maintained order in swap shed;
  • Cleaned the trailer pit as needed;
  • Pick up litter and cleaned up around the site as needed
2
de-icing spreader spinning

Highway/Stormwater Divisions

  • Hot patching potholes: north, middle and south sections;
  • Skin overlay degraded roadway surfaces:  Nobscot Road, Shady Hill Road, Hickory Road;
  • Respond to Misc. calls for service:  clear illegal leaf dumping into culvert;
  • Pickup deer removals:  Cliff Road;
  • Traffic signage and maintenance repairs: Old Road and Cherry Brook Road;
  • Respond to miscellaneous calls for service;  
  • Respond to flooding calls: Kendal Common;
  • Check and clear waterways: Glen Road, Shady Hill Road, south section;
  • Clean and service equipment;
  • Organize and re-stock stormwater shop;
  • Snow and ice mobilization:  12/31 to 1/1 - 1 general deicing event;
  • Transport waste aggregate to disposal vendor;
  • Oversee drain line cleaning / video contractor:  Shady Hill and Long Meadow Road;
  • Driver Training (S-11 Catch Basin Cleaning Truck) – in-house;
  • Driver Training:  Sander Training for new employee and Sidewalk Plow Training for new employee
 
maintenance of a DPW truck

Vehicle Maintenance Division

  • Performed routine maintenance (fluid services, tires and brakes, exhaust, steering and suspension, exterior trim work and electrical repairs) on 6 school buses, 2 police vehicles, 7 DPW trucks and other equipment, and 1 school grounds vehicle, noting that the DPW Vehicle Maintenance Division is responsible for over 122 pieces of rolling stock for the Town;
  • Performed 2 major repairs on vehicles with Major/Significant maintenance activity:  G-1 ball joints and Bus No. 18 brake lines and alternator;
  • Assisted the Highway Division with sanding 12/31 to 1/1 operations
 