September 27 to October 3, 2020The Weston Department of Public Works continued to fulfill its mission to construct and maintain the physical infrastructure that provides for the public's health and safety, to protect the environment, and to enhance the quality of life and ensure that Weston continues to be a desirable place in which to live and conduct business. The following is the weekly report, by division:
|
|
|
|
2020 Roadway Reconstruction ProgramThe Public Works team is well into its design and permitting work for this season's roadway reconstruction and utility work. There is a great deal of planning and coordination that goes into the overall roadway schedule and the annual roadway construction activities that also involve associated drainage, culvert, water, sidewalk, and utilities (National Grid) work. Depending on how well the coordination progresses, DPW is expecting to begin Round 1 of the roadway reconstruction work and utility work in June 2020. Roadways anticipated for the 2020 construction season (some are dependent upon the completion of water, drainage, and gas work): - Kings Grant Road (Spruce Hill Road to cul de sac) - Binder pavement course, then standard roadway work outstanding (e.g. raise structures (anticipate completing week of October 5 ), top course of pavement installation anticipated the week of October 12 , loam and seed, etc.);
- Indian Hill Road (Kings Grant Road to end) - standard roadway work outstanding (e.g. raise structures, top course of pavement installation, loam and seed, etc.);
- Winthrop Circle - Standard roadway work outstanding (e.g. raise structures, top course of pavement installation, loam and seed, etc.);
- Merriam Street* - Silver Hill Road to Sunset Road - Binder course of pavement installed at the culvert. Structures adjustments completed. Upright Berm locations are laid out and installed. Final pavement installation anticipated in a few weeks
*Merriam Street (Sunset Road to Silver Hill Road) – Expect Merriam St. road closure & detours while the existing culvert is removed and the new one is installed. Work will include the water main replacement in the culvert area. The contractor will be responsible for all signage. Work is anticipated to take appx 8 weeks, though is weather dependent.There are a lot of moving parts that need to be completed prior to the Merriam Street reconstruction taking place, including: - Merriam Street Culvert Replacement over Cherry Brook - Outstanding work: berm, guardrail (after berm is installed), and top course of pavement, and then pavement markings;
- Sidewalk installation (southerly section between Westland and Sunset roads) - Structures were raised in preparation of berm placement final paving work, Upright Curbing laid out and installed throughout the project area, sidewalk gravel installation ongoing, then two layers of sidewalk pavement will be installed prior to final paving of roadway; Boardwalk installation ongoing (i.e. end treatments);
- Merriam Street (Sunset Road to Westland Road) paving – schedule dependent on above
2020 Completed Roads- Ash Street (mill and overlay)
- Church Street (mill and overlay)
- Merriam Street drainage work completed between Westland Road and house no. 189 +/-, Westland Road and house no. 217, and house no. 245 +/- to Hallet Hill Road;
- Arrowhead Road
- October Lane
- Webster Road
ROAD CUTTING AFTER PAVING MORATORIUM - once paving is completed on any roadway in Weston, a five-year moratorium on pavement cutting is placed on that road. This is done to protect the investment made by taxpayers. A five-year schedule of anticipated roadway reconstruction is available on the DPW's web page under Capital Improvement Projects. 2020 Deferred Roads (anticipate 2021 season)
- Bay State Road - Spruce Hill Road to end
- Buckskin Drive - Route 20 to town line
- Newton Street (No. 150 +/- to South Avenue) – Drainage work needs to be completed.
- Spring Lane (Conant Road to end of roadway)
- Spruce Hill Road - Kings Grant Road to cul de sac
- Warren Avenue
- Bogle Street (rubber chip seal)
- Conant Road (rubber chip seal) – Colchester to Brook Road
Town Center Improvement ProjectFind construction updates - sign up for "Town Center Construction Project" email/text notifications Weston.org/StayInformed or visit project web page at Weston.org/TownCenter for three-week look ahead and project views. Ongoing- Work in Town Square, Knox Park, and The Terraces
- Curbing and sidewalk work along south side of BPR, Sidewalk/walkway work in front of several businesses being coordinated with said businesses
- Eversource pole set work and overhead wire transfers
- Businesses are open and parking is available, follow signage
Anticipated work over the next several weeks: Town Square work, Eversource pole set work and overhead wire transfers ongoing, curbing and sidewalk work on the south side ongoing, etc. The Town Square stone work and grading work ongoing. Sidewalk/walkway work in front of several businesses being coordinated with said businesses. Additional Road Work Not Affiliated with the Town's Roadway Program
- See updates in "State/Utility Project Work" for projects impacting roadways:
- National Grid gas main work
- Coordinated gas main replacement through DPW
|
|
|
|
State/Utility Project Work- Continuing to coordinate with Eversource on a number of outstanding issues in Town including double poles, poles guyed into trees, leaning poles and pole guyed with rope (Merriam Street), Hazard trees at/near power lines, etc.;
- National Grid has submitted several permits for repairing long-standing gas leak locations;
National Grid Gas Relay ProjectsProposed work for the 2020 Construction Season. - Sherburn Circle and Tyler Road – Gas Main work ongoing. Anticipate the NGrid crew will be on site for the duration of this construction season;
- Concord Road ( 1-81) - NGrid is also obligated to complete necessary restoration work (pavement, curbing, grass, etc.). Schedule has yet to be determined but it will have this construction season;
- 292-352 Winter Street – Gas Main work ongoing. Service work ongoing and according to NGrid crew they anticipate being completed by the end of October 12 week. They still have the pavement restoration obligations which will take place next construction season in the spring 2021;
- 74-147 Orchard Avenue (private roadway) – NGrid still has restoration requirements on this private roadway;
- 4-54 Orchard Avenue (private roadway) – No schedule provided by NGrid
Finished work for 2020:- Wellesley Street (from 654 to 699)
- Webster Road
- Indian Hill Road
- Baystate Road
|
|
|
|
Ongoing DPW Projects & Consultant Work- Wireless Meter Reading - Permits for collector are in progress. Notices for meter work and scheduling will be going out soon. Coordination with town accounting hardware ongoing (MUNIS). Anticipate antenna poles being delivered week of August 24 and then construction of said pole there after.. See Weston.org/WaterMeters for more project information;
- Southside Drainage – Phase III – Contract being executed and anticipate design and permitting starting up mid-October 2020. Goal is to get design and permitting and securing necessary easement completed over the winter and be in construction next construction season (2021);
- Newton Street Drainage (by church and Doublet Hill Area) - Town Engineer is working with several properties owners and others to secure easement rights for Phase II and Phase III drainage work;
- Legacy Trail Project - Construction nearing completion;
- Overseeing consultant work on Proposed Route 30 Roadway Reconstruction TIP Project (roadway, sidewalk, drainage improvements, intersection improvements, etc.) - approval of 25% plan submission was approved by the Board at a September 24, 2020 meeting. Formal 25% Submission to MassDOT in the next couple of weeks (October 2020). Project info at weston.org;
- Overseeing consultant work on Proposed Route 20 Intersection Improvement TIP Project - (signal at Boston Post Road/Wellesley Street/Boston Post Road By-Pass) - 25% Plans submitted to MassDOT on March 16, 2020. Awaiting review comments, then a MassDOT Pubic Hearing anticipated for October/November 2020. Project info at weston.org;
- Overseeing consultant design and permitting for Concord Road Culvert replacement which has impacts on the Warren Avenue and Merriam Street culverts - decision matrix tabling being evaluated. Engineering presented findings to Board of Selectmen and the Conservation Commission;
- Overseeing consultant design and permitting for Ash Street Sidewalk Project - Design ongoing. Consultant to presented progress prints to Traffic and Sidewalk Committee, but drainage, length of crosswalk and curbing issues/comments from DPW Director need to be resolved. Town Engineer has outreached to MWRA about secure rights / easements to address previously mentioned concerns;
- Overseeing consultant design and preparation of specification for Cemetery Tomb Restoration. Central Cemetery - work ongoing
|
|
|
|
Engineering- Currently reviewing 14 Stormwater Permits;
- Currently issued 51 Stormwater permits which also requires construction inspection;
- MS4 Stormwater Permit Annual Report:
- Currently in Year 3 of the MS4 Permit
- Submitted Year 2 Annual report on September 28, 2020, with requirements including: Updating Minimum Control Measures that are required for MS4 - Year 2 and Year 3; SWPPP for the DPW Building and the Transfer Station started; completed IDDE training for Year 2. The MS4 Educational outreach material and messages are an ongoing goal of the MS4 Permit and continue to been posted on the Town web pages and Town social media messages
- The consultant, Environmental Partners, is scheduled to continue to work on the planned Phosphorous Control Plan for the MS4 Permit during Year-3
- The preparation of the Phosphorous Control Plan/Ordinance update began in Year-2 (Fiscal Year 2020), and is to be completed in Year 3 (Fiscal Year 2021) of the MS4 Permit
- Catch Basin Cleaning – Completed;
- Working with the Town’s Traffic and Sidewalk Committee on several items: Love Lane, Chestnut Street, Sunset Road, Wellesley Street at Route 30 signal, mirrors, stop sign requests, sidewalk requests, crosswalk requests, etc.;
- Engineering Drainage Designs Ongoing / Construction Bid Documents advertised after funding approval at Sept. 2020 Town Meeting:
- Hallet Hill at Merriam Street – Plans completed; Boring work outstanding; Finalizing easement plan for Hallet Hill so appraisal can be finalized;
- Newton Street – Newton Street drainage design and plans complete; survey working on easement plan; NOI has been submitted for the Newton Street (MWRA) section of the proposed drainage;
- Kings Grant Road – Plans complete with possible minor updates in the field; test pits completed and determined good soil conditions for infiltration unit(s);
- Pinecroft at Conant Road – Design and plan prep. plans completed;
- Rolling Lane – Design and plan preparation to be completed;
- 520 Glen Road – Wetland delineation completed and report submitted; survey complete; NOI submitted.
|
|
|
|
 The Brush Dump opens for six consecutive Saturdays starting October 17th. The Transfer Station also accepts yard waste. If you don't have a Transfer Station permit, you can get a Recycle Only permit for your yard waste and other recyclables. Visit Weston.org/TSPermits for information on obtaining one of these permits.
|
|
|
|
|
|
|
|
Water Division- Completed approximately 36 DigSafes;
- Performed weekly samples (3), monthly water samples at tanks, and station/tank inspections;
- Conducted 1 final read;
- Inspected 1 new water service;
- Next week will begin our COVID delayed hydrant flushing program starting in the South section of Town;
- Disconnected 1 temporary water meter;
- Turned on new section of water main at Merriam Street culvert (under new culvert);
- Responded to 1 low pressure call;
- Responded to 1 water quality call
|
|
|
|
Park and Cemetery Division- 1 cremation interment;
- Mowed and string trimmed around Linwood Cemetery, Central Cemetery, Main Library, Old Library, Fiske Park, Fiske House, DPW and Police Station;
- Set 1 flush marker;
- Serviced equipment;
- Washed trucks;
- Removed invasive weeds and pruned shrubs at Case Park;
- Watered newly planted trees and shrubs around Town
|
|
|
|
Solid Waste and Recycling Division- Processed 1, 100-yard solid waste dumpster totaling 22.54 tons;
- Picked up municipal office recycling – 1,420 lbs;
- Picked up Town office and select town park solid waste – 940 lbs.;
- Processed 2 cardboard containers – 6.61 tons;
- Processed 1 container of plastic – 3.84 tons;
- Ran 1 shuttle for grass/leaves – 11.53 tons;
- Ran 2 shuttles for brush /logs – 12.39 tons;
- Processed 1 metal container – 5.08 tons;
- Process 1 container of scrap wood – 3.88 tons;
- Assisted with the pickup of various donations including clothing, electronics, books and bikes – 4,040 lbs;
- Processed 5 cent deposit bottles and cans – 1,080 tons;
- Cleaned the trailer pit as needed;
- Pick up litter and cleaned up around the site as needed;
- Packed containers as needed to maximize loads;
- Disinfected Solid Waste and Recycling areas daily;
- Mowed around the Transfer Station;
- Rebuilt chute for Newspaper Bin;
- FOOD COMPOSTING – To begin soon based on Select Board vote on October 1st;
- BULKY WASTE COLLECTION CHANGES coming January 1, 2021.
|
|
|
|
 To help Weston residents reduce what they put in the trash bag and get acquainted with the benefits of composting, a pilot program has been initiated at the Transfer Station. Look for green bins near the trash hoppers to dispose of your fruit and vegetable scraps and a lot more! No permit sticker? No problem, visit Weston.org/TSPermits
|
|
|
|
Highway/Stormwater Divisions General:
- COVID-19: Personnel and Equipment SOPs;
- Respond to Misc. calls for Service – 25;
- Traffic Detours Setup & Removals: Kings Grant, Indian Hill, Bradford, Plymouth;
- Employee In/Out of House Training: Flail;
- Cooks Pond Pump Station (drainage): 9/28, 30 and 10/1 pump operating normally;
- DIGSafe Markouts & Permits Requested: Viles, Oxbow;
- Deer Removal: South Avenue at Park Road;
- Cleaning and Servicing Equipment: As needed
Outside of Division:
- Assist Park/Cemetery/Transfer Station Division: compact dumpsters. Remove counterweights from Central Cemetery;
- Assist Fleet Maintenance: Oil spill on South Avenue;
- Assist Police Department: Received call for car accident debris on Wellesley Street and Woodchester, Two trash bags on South Avenue;
- Assist Paving Contractor (Lazaro) – Merriam, Kings Grant Road, Indian Hill, Wintrop;
- Assist Drainage & Video /Jet Cleaning Contractor – Bay State, Hancock
Highway - Inspect Roadway Conditions: Concord Road;
- Screen and Remove waste gravel material from Upper Yard;
- Sign and Mailbox Repairs and Installations and fence repairs: New Speed Zone Signs Installs @ Town Lines and continue fence repairs on School Street;
- Remove debris from roadway: Class and car parts;
- Wall Inspections and/or Repairs: Inspection at Viles;
- Sidewalk Sweeping: Church Street;
- Mowing and trimming Islands and Grass Strips: All sections;
- Flail Mowing: section on South Avenue, section on Wellesley Street, Newton Street and Ridgeway;
- Inspect Tree Locations: Concord at Nottingham;
- Tree and/or Branch Removals and Debris Cleanup: Warren Avenue, Bradford Road, Webster, Highland, Wellesley, Ellis, and Spruce Hill;
- Tree Canopy Raising and Trimming: Kings Grant area;
Stormwater - DMH/CB Inspections & Roadway ID Markings: Kings Grant Area;
- Catch Basin Inspection, Sinkhole, rebuild/replace, repave: Hancock at Kings Grant
Winter Operations – WINTER IS COMING……..
|
|
|
|
Vehicle Maintenance Division- Performed routine maintenance (fluid services, tires and brakes, exhaust, steering and suspension, exterior trim work and electrical repairs) on 6 school buses, 3 police vehicles, 18 DPW trucks and other equipment, and 1 school grounds vehicle, noting that the DPW Vehicle Maintenance Division is responsible for over 127 pieces of rolling stock for the Town;
- Performed 4 major repairs on vehicles with Major/Significant maintenance activity: H-22 hydraulic leak, H-15 fuel hose, S-1 all wheel brakes, and 8 bridge inspections;
Fuel island, weekly inspection performed; - Performed 1 repair on sanders/plows: H-11 sander install and prepare for winter;
- Road Call: Bus 14 and H-22;
- Assisted with bus launch for schools
|
|
|
|