Town Square Exhedra installation
Expect more progress on the new Town Square

Construction Update - September 21


Access to homes and businesses will always be maintained. Police Detail is on site. Follow signs for business parking or ask for help.

This week, the following work is expected:

  • Town Square work:
    • sidewalk installation
    • Exhedra
    • planter curb
    • granite, brick, and cobble paving
  • Installation of the remaining curb in the Brother's parking lot
  • Pavement milling at:
    • Town House Road (no parking in area of work, driving access will remain)
    • Church Street
    • Brother's parking lot (night work after closing)
  • Installation of the irrigation mainline
  • Install concrete base slabs in all locations
  • Secondary and lighting cable pulls
  • miscellaneous work at various locations
  • Construction is continuing under approved conditions, as outlined by the state


See the Three-week Look Ahead Schedule (PDF) for the anticipated upcoming schedule.


General visual depictions of the upcoming surface work can be found on the Project Summary and Project Views  web pages. This also includes the historical context of the Town Green District.

town center improvement project



Please consider sharing this email and information.

You may subscribe to receive these email/text notifications of construction activities on the “Town Center Construction Project” under "News Flash" at www.weston.org/StayInformed. 


Questions/Comments about this notice may be sent to webmaster@westonma.gov

Share on Facebook
Share on Twitter
Share via Email

Copyright 2020 Weston, Mass. All Rights Reserved.
11 Town House Road, Weston, Mass. 02493
Comments can be sent to webmaster@westonma.gov

Powered by
CivicSend - A product of CivicPlus