town center improvement project view

Construction Update - May 11th - Sidewalk Work Begins


Access to homes and businesses will always be maintained. Police Detail is on site. Follow signs for business parking or ask for help.

See the Three-week Look Ahead Schedule (PDF) for anticipated schedule.  

  • Foundations at Knox Park and Terraces
  • Sidewalk stripping on Boston Post Road, from Fiske Lane to Concord Road
  • Raise frames and covers in roadway for utility company access
  • Set curbing at Brother’s Marketplace lot, Boston Post Road from Fiske to Concord and Town House Road to Church St

Construction is continuing under approved conditions, as outlined by the state.


Project Views

General visual depictions of the upcoming surface work can be found on the Project Summary and Project Views web pages. This also includes the historical context of the Town Green District.

Parking


If you require access to a business, please ask for assistance if access is unclear.
  • Pedestrian access to businesses will be maintained. 
  • If you need assistance accessing a business, please ask a police officer or ground crew member. 
  • If crews are working in front or near a retail shop, please look for signs indicating alternative parking areas. 
NO PARKING signs will be posted 24-hours in advance of road work. Barrels will be placed in the spaces that will not be available for parking. We ask that you take notice of these signs and refrain from parking in these areas during the posted hours. If the barrels are placed up on the sidewalk, then parking is allowed in the space.



Anticipated Work & Hours

Day work will begin at 7:00 a.m. and generally conclude around 3:00 p.m., though some days may go a bit longer. Anticipate site set up to occur prior to 7:00 a.m.

Refer to the "Three-week Look Ahead" document below for anticipated upcoming work. This document is updated weekly. 
  • Three-week Look Ahead (PDF) 
As with all construction work, activities are anticipated as unexpected issues can arise and delay progress.

Follow Progress and Get Updates

Construction updates, detours, potential schedule changes, and progress will be posted on the project web page at www.weston.org/TownCenter and will be issued through this dedicated project email/text service.

You may subscribe to receive these email/text notifications of construction activities on the “Town Center Construction Project” under "News Flash" at www.weston.org/StayInformed. 


Construction progress photos are posted online.


Please consider sharing this email and information.



Questions/Comments about this notice may be sent to webmaster@westonmass.org

Share on Facebook
Share on Twitter
Share via Email

Copyright 2020 Weston, Mass. All Rights Reserved.
11 Town House Road, Weston, Mass. 02493
Comments can be sent to webmaster@westonmass.org

Powered by
CivicSend - A product of CivicPlus