2020 Roadway Reconstruction Program - In Development
The Public Works team is developing its FY21 budget, which includes planning the next construction season activities and engineering design and permitting work.
There is a great deal of planning and coordination that goes into
the overall roadway schedule and the annual roadway construction activities that also involve associated drainage, culvert, water, sidewalk, and utilities (National Grid) work. Depending on how well the coordination progresses, DPW will begin the roadway reconstruction work and utility work sometime in April 2020. Residents can expect another aggressive construction season, which will be managed and balanced with the Town Center Project, as that work moves above-ground, and the start of the Josiah Smith Tavern rehabilitation (overseen by the Facilities Dept.).
Roadways currently under review for the 2020 construction season are the following (some are dependent upon the completion of water, drainage, and gas work):
- Bogle Street (round 2 of the Rubber Chip Seal program);
- Conant Road (round 2 of the Rubber Chip Seal program) – Colchester to Brook Road;
- Ash Street (mill and overlay);
- Church Street (mill and overlay) – Conant Road to railroad;
- Kings Grant Road - Spruce Hill Road to cul de sac;
- Spruce Hill Road - Kings Grant Road to cul de sac;
- Bay State Road - Spruce Hill Road to end;
- Indian Hill Road - Kings Grant Road to end;
- Webster Road - Church Street to Church Street;
- Buckskin Road - Route 20 to town line;
- Warren Avenue - Boston Post Road to Gun Club Lane;
- Arrowhead Road - Bakers Hill Road to Bakers Hill Road;
- Merriam Street* - Silver Hill Road to Sunset Road;
- Newton Street - #150 to South Avenue;
- October Lane - Bakers Hill Road to Conant Road;
- Spring Lane - Conant Road to end of roadway
*(Remaining) 2019 Roadway Reconstruction Program
Merriam Street (Sunset Road to Silver Hill Road) – a lot of moving parts remain and need to be completed prior to the roadway reconstruction taking place. These include
completing the roadway drainage work between Westland Road and house no. 189 +/-, Westland Road and house no. 217, and house no. 245 +/- to Hallet Hill Road;
Merriam Street Culvert Replacement over Cherry Brook; water gate replacements on Merriam Street at Cherry Brook Road (utility pole
holding is required by Eversource); and the sidewalk installation (southerly section between Westland Road and Sunset Road require easements)
2019 Paving Season Totals
- 28,636 linear feet - about 5.42 miles of roadway, including 6,216 linear feet of chip sealing on Brown Street and Cliff Road (first year program)
- 26,844 linear feet of crack sealing (second year program)
- about 3,775 linear feet (appx .7 miles) of sidewalks and curbing were rehabilitated
- two new parking areas at Concord Road and Church Street were installed for the Mass Central Rail Trail
- and 100 linear feet of new sidewalk was installed at the Church Street spur for the rail trail
Town Center Improvement Project
Find
construction updates - sign up for "Town Center Construction Project" email/text notifications
Weston.org/StayInformed or visit project web page at
Weston.org/TownCenter for three-week look ahead.
- Businesses are open and parking is available - traffic Management Plans are modified daily to maximize available parking for the businesses;
- Manhole and conduit work and structure service work installation ongoing
Additional Road Work Not Affiliated with the Town's Roadway Program
- See updates in "State/Utility Project Work" for projects impacting roadways:
- National Grid gas main work
- Coordinated gas main replacement through DPW
- See updates in "Ongoing DPW Projects" for water/drainage, etc. work at:
- Newton Street
- Legacy Trail
- See updates in "Consultant Work" for larger projects at:
- Rt. 20 and Rt. 30 TIP projects
- Ash Street sidewalk